BUILD #11, 2010
TENATIVE WORK SCHEDULE
February 18, 2010
# of workers needed
Wednesday April 29th Excavate hole, install water and sewer line 2-4
Saturday, May 1st Build footer forms 4-6
Monday, May 3rd Pour footers 6-8
Saturday, May 8th Lay block 3-4
Monday, May 10th Insulate block wall/ Install plate
Tuesday, May 18th Build house floor with students 10-12
May 20th & 21st Raise exterior walls with students 16
Saturday, May 22nd Raise trusses and build roof 6-8
Monday, May 24th Start interior walls 4-6
Saturday, May 29th Shingles 6-8
Week of:
Saturday, June 5th Concrete work, Electrical, Plumbing, Heating,
Exterior Paint and Insulation
Saturday, June 12th Windows, Doors and Siding 12-16
Saturday, June 19th Start Hanging Drywall (Cordless drivers needed) 10-12
Saturday, June 26th Drywall Finishing and Painting
Saturday, July 3rd Drywall Finishing and Painting
Saturday, July 10th Interior doors, trim and attic insulation 4-5
Saturday, July 17th Flooring and Cabinets
This schedule is meant to be used as a guideline The only thing definite about it is that it will change as a result of weather, sub-contractor scheduling or lack of volunteer labor