BUILD 009, 2008

WORK SCHEDULE

April 17, 2008

 

                                                                                                                                                                             # of workers needed

May 15th and 16th Dig hole

 

Week of May 19th  Pour and Paint footers.  Install gravel. 6-8

 

Saturday,  May 24th Lay block                                         6

 

Week of May 26th Install plate and insulate foundation and       

                                                start framing the floor     6-8 

                                              

Saturday, May 31st Finish building deck, if necessary.          6-8

 

WEEK OF

Saturday, June 7th  Raise all walls and roof                       20-25

 

Saturday, June 14th Shingles                                           15-20     Concrete work, Electrical, Plumbing, Heating, Exterior paint and Insulation                                      

 

Saturday, June 21stWindows, Doors and Siding                  15-20

 

 Saturday, June 28th  Start Hanging Drywall                      12-16

                                     (Cordless drivers needed)

Saturday, July 5th     Drywall finishing and painting                      

 

Saturday, July 19th Interior doors, trim and attic insulation   4-5          

 Saturday, July 26th    ………          Flooring and Cabinets

 

 

This schedule is meant to be used as a guideline.  The only thing definite about it is that it will change as a result of weather, sub-contractor scheduling or lack of volunteer labor.